US Ferc Sets Schedule for Gateway Expansion Review
The US Federal Energy Regulatory Commission (Ferc) on May 24 set the schedule for the environmental review of Transco’s 65mn ft3/day Gateway Expansion Project.
Ferc staff expect to issue an environmental assessment of the project on July 17, 2018, triggering the 90-day federal authorisation decision deadline of October 15, 2018.
Advertisement: The National Gas Company of Trinidad and Tobago Limited (NGC) NGC’s HSSE strategy is reflective and supportive of the organisational vision to become a leader in the global energy business. |
The expansion project consists of the addition of 33,000 hp of electric-drive compression at Transco’s Compressor Station 303 in Essex County, New Jersey, and meter, regulator, transformer and ancillary equipment installations at the Roseland and Paterson meter stations, also in New Jersey.
Cost of the expansion project is estimated at $84.6mn, and the new facilities are expected to be in service by the 2020/2021 winter heating season.