• Natural Gas News

    Production at Gorgon LNG Project Estimated to Restart in 30-60 Days

    old

Summary

Chevron on Wednesday said production at the Gorgon LNG project is expected to restart within 30-60 days.

by: Shardul

Posted in:

Asia/Oceania

Production at Gorgon LNG Project Estimated to Restart in 30-60 Days

Chevron on Wednesday said production at the Gorgon LNG project is expected to restart within 30-60 days.

The project on Barrow Island off the northwest coast of Western Australia has been temporarily halted due to mechanical issues with the propane refrigerant circuit on Train 1 at the plant site.

First LNG production started on March 7 with peak production touching nearly 90,000 barrels of oil equivalent per day. The first LNG cargo departed Barrow Island on March 21 and has been delivered to Chubu Electric Power in Japan.

“The propane refrigerant circuit is a closed system used to cool natural gas supplied to the plant. Work necessary to complete the repairs is ongoing while the site team continues equipment inspection and assessment. Based on initial findings, the repair work is of a routine nature and all the necessary equipment and material is available on site. A restart of the plant within 30-60 days is estimated at this time,” the company said in a statement.

Train 1 ramp-up to full capacity is still expected to occur over 6 to 8 months from initial start-up of the facility. Meanwhile, construction activities continue to progress on LNG Trains 2 and 3 with timing not affected by the work on Train 1, Chevron said.

The Chevron-operated Gorgon Project is a joint venture between the Australian subsidiaries of Chevron (47.3 percent), ExxonMobil (25 percent), Shell (25 percent), Osaka Gas (1.25 percent), Tokyo Gas (1 percent) and Chubu Electric Power (0.417 percent).