Poyry has been awarded an four-year owner's engineer services assignment for a 1,440 MW natural gas-fired combined cycle power plant in Johor, Malaysia by Southern Power Generation.

by: Shardul Sharma

Posted in:

Natural Gas & LNG News, Asia/Oceania, Gas to Power, Contracts and tenders, News By Country, Malaysia

Poyry Wins Malaysia Plant Contract

Poyry has been awarded an four-year owner's engineer services assignment for a 1.44-GW natural gas-fired combined-cycle power plant in Johor, Malaysia by Southern Power Generation, it said January 5.

Southern Power Generation is a project company established for this independent power producer project and owned by Malaysian state-owned power utility Tenaga Nasional and SIPP Energy. 

The project consists of two 720 MW natural gas-fired combined cycle blocks, with distillate as backup fuel. The plant will be located adjacent to the existing Sultan Iskandar Power Station at Pasir Gudang, Johor. 

Poyry's assignment includes assistance in project management, design review, site supervision services, quality assurance and quality control, commissioning supervision services and services during warranty period. Poyry will be assisted by its local partner, Minconsult.

The value of the order was not disclosed.