    Philippines' First Gen seeks one LNG cargo for FSRU commissioning in Sept

Summary

Philippine power producer First Gen Corp will issue a tender probably in the next two weeks for one liquefied natural gas (LNG) cargo for delivery in September, a company official said on Wednesday.

by: Reuters

Posted in:

Complimentary, NGW News Alert, Natural Gas & LNG News, Asia/Oceania, Liquefied Natural Gas (LNG), Infrastructure, News By Country, Philippines

Philippines' First Gen seeks one LNG cargo for FSRU commissioning in Sept

MANILA, May 17 (Reuters) - Philippine power producer First Gen Corp will issue a tender probably in the next two weeks for one liquefied natural gas (LNG) cargo for delivery in September, a company official said on Wednesday.

The company expects to commission its floating storage and regasification unit (FSRU) in Batangas province, about 92 km (57 miles) south of capital Manila, in September, and is looking for an initial LNG cargo of 160,000 cubic metres, said chief commercial officer Jonathan Charles Russell.

Advertisement:

The National Gas Company of Trinidad and Tobago Limited (NGC) NGC’s HSSE strategy is reflective and supportive of the organisational vision to become a leader in the global energy business.

ngc.co.tt

S&P 2023

"We're in parallel discussions for a medium- to long-term supply (deal), those are ongoing with a number of different entities," he told reporters on the sidelines of the company's annual stockholders' meeting.

"But for now, we're prioritising the spot tender, so we can get the project in operation."

First Gen's FSRU is one of the seven LNG import terminal projects approved by the government, as the Southeast Asian country switches to imported LNG to ensure uninterrupted operation at several power plants currently running on its Malampaya natural gas.

First Gen owns four power plants with a combined capacity of about 2,000 megawatts and all of them run on supply from the Malampaya gas field.

The field may run dry by 2027 if no further development and new exploration are undertaken around the site, according to the government.

The medium- to long-term LNG supply deal that First Gen aims to clinch may start in 2024 at the earliest, Russell said.

The initial LNG cargo that First Gen is seeking could last for one to three months, "after that (there may be) another tender or we will commence a medium-term contract", he said.

(Reporting by Enrico Dela Cruz; Editing by Subhranshu Sahu)